 Gypsemna will be the first world-scale plasterboard plant in the Middle-East with a capacity of 50 million Sq M per annum.      Global Gypsum Conference will be held in Dubai on 12th & 13th May, 2008.
Jamal Al Ghurair Group

Mr. Jamal Al Ghurair belongs to the Al Ghurair family, one of the most highly respected family business houses in Dubai which has established diversified business enterprises in sectors like aluminium, cement, sugar, real estate, retail, shopping malls, packaging, mineral water, insurance, banking etc.

 
 
Group Web Sites
Al Khaleej Sugar
Porcellan

Current vacancies
Careers

Business Opportunities
Contact us

Contacts
Abu-Dhabi office
Dubai office

About Gypsemna

Gypsemna Company (L.L.C) is a new company promoted by Mr. Jamal Majid Al Ghurair and Mr. Khalid Jamal Al Ghurair, to set up a world-scale plasterboard factory in Abu Dhabi

Mr. Jamal Al Ghurair, a prominent member of the Al Ghurair family of Dubai, is the main promoter of the world scale gypsum plasterboard plant being set up in the industrial zone of the Emirate of Abu Dhabi.

The plant, located at Industrial City of Abu Dhabi, will have an initial installed capacity of 50 million Sq Meters per year, based on a line speed of 90 Meters per minute. Thus the plant is expected to be the first high speed line for plasterboard production in the region. The plant is one of the new projects being implemented by Mr. Jamal Al Ghurair (of Al Khaleej Sugar Company, Dubai) in the building materials sector and is expected to substitute imported plasterboard required for the booming construction industry of the United Arab Emirates and the nearby Gulf Co-operation Council countries

The main contract with Grenzebach GmbH, a reputed German Machinery Supplier, includes supply of roller mill calcining system and the complete production line for plasterboard with equipment incorporating latest technology. Grenzebach completed the delivery the plant during the third quarter, 2008.

 

Project Status (As in Dec 08)

  • Land allotment : 19th April, 2006
  • Industrial License from HCSEZ: Issued on 1st May 2006
  • Environmental Permit : Issued on 8th Nov, 2006.
  • Site Construction activities : Commenced on 15th Jan 2007
  • Factory Main Building Completion : Jun 08
  • Start of Shipment of major process equipment : Jun 08
  • Receipt of all equipment at site from Main supplier : Nov 08
  • Completion of Erection : Feb 09 (Scheduled)
  • Commissioning of the Plant : Mar 09 (Scheduled)
  •